|
Hugo Plant
The Hugo Plant, a 450 net megawatt coal-fired generating
unit located near Fort Towson, Okla., began commercial operation
April 1, 1982. Water and coal are its primary ingredients
in the production of electricity and huge volumes of both
are supplied to keep the plant operating.
Water is taken from the Kiamichi River, downstream from
the Hugo Reservoir, and is pumped through a 42-inch diameter
pipeline to the 80-acre holding pond on the plant site.
The water is cleaned in the water treatment plant before
it is used in the boiler and cooling towers. The water treatment
plant is large enough to supply the needs of a city with
a population of 50,000 people. The Hugo Plant can use up
to 11,000,000 gallons of water per day.
When operating at peak capacity, the plant can burn approximately
275 tons of coal per hour. That need is primarily supplied
by the deposits of low-sulphur coal in the Powder River
Basin area near Gillette, Wyoming. The coal seams there
are thick enough to be economically surface-mined.
Coal is delivered to the plant by train and the1,340-mile
journey from the mine ends at the plant as the railcars
are emptied by the rotary dumper. Conveyors move the coal
into the plant where it is ground to powder consistency
and then blown into the boiler and burned.
The exhaust coming out of the boiler is cleaned before it
is discharged through the 500-foot tall stack. An electrostatic
precipitator removes lightweight fly ash to storage silos
for sale as a concrete admixture. The heavier bottom ash
falls to the bottom of the boiler and is transported to
holding ponds. The exhaust gas coming out of the stack is
constantly monitored to meet environmental guidelines.
Mooreland Plant
The first unit at the Mooreland Plant began operating on
March 27, 1964; a second unit came on line on May 13, 1968;
and the third unit first delivered power on April 29, 1975.
All three units were built by Westinghouse and have a combined
output of 304 megawatts. Like other turbines and generators,
they are powerful and heavy. Unit number one weighs about
400,000 pounds and is rated at 58,666 horsepower. Units
two and three are rated at 166,666 and 180,000 horsepower
respectively and weigh about 995,000 pounds each.
All units at the Mooreland Plant use conventional natural
gas-fired boiler and steam turbine design. The Mooreland
Plant, like the Anadarko Plant, is supplied with gas by
WFEC's natural gas pipeline. At peak capacity, the three
units would burn approximately 2,500,000 cubic feet of gas
per hour.
Anadarko Plant
The Anadarko Plant first generated electricity in 1953.
The original generator, a 15 megawatt Elliot, is still in
operating condition on standby status. A second and third
unit added later brought the capacity of the plant up to
74 megawatts.
The original plant uses a conventional gas-fired boiler
and steam turbine method of power generation. The three
units, two Elliots and one Allis Chalmers, have provided
many thousands of hours of service and were the best of
the available designs of their day.
In 1977, a new type of unit began operating at the Anadarko
Plant. Called a Combined Cycle unit, the new design operates
much like a turbofan jet engine on an airplane. These new
units have attracted visitors from around the world who
come to see first-hand the efficiency of the units. The
new units added 300 megawatts of generating capacity.
The Combined Cycle units are so named because they combine
gas turbine and steam turbine power to turn the generator.
First, natural gas is burned as fuel and the hot; expanding
exhaust is directed over the turbine blades causing them
to turn like a jet engine.
The exhaust is then channeled into a small boiler where
the heat creates steam that is piped into a steam turbine
connected to the same generator as the gas turbine. This
method gets the maximum amount of work out of the fuel by
using as much of the fuel's energy as possible.
Each of the three Combined Cycle units is rated at 100 megawatts
and weighs 831,297 pounds. They are housed in the newest
portion of the Anadarko Plant, adjacent to the original
plant. The original cost of building the total plant was
$78,594,000.
Water for the plant is taken from Fort Cobb reservoir. About
2,000,000 gallons is used or recycled each day the plant
is in operation. The water is demineralized for use in the
boilers and treated with chlorine bleach for use in the
cooling towers.
Fuel for the plant is delivered by WFEC's 357 miles of 16
and 8-inch diameter natural gas pipeline system which connects
the plant to the rich gas fields in western Oklahoma. If
operating at peak capacity, the total Anadarko Plant could
burn 80,040,000 cubic feet of natural gas in a 24-hour period.
|